Case Studies

Our case studies are designed to

offer you valuble information about

our pioneering cleaning systems.

For more information please

do not hesitate to contact us.

The Impossible Render Clean - Render Cleaning

A complex project, with logistical and political intricacies read on to find out how we managed to fully restore the external façade of Ursa Court with limited disruption to locals or residents.

The Housing Association was able to save £120K on access costs over 3 decorating cycles!

The Project

The Impossible Render Clean

Render Cleaning

  • Location:Brighton
  • Client:Brighton Housing Association 
  • Project Duration:28 Days
  • Substrate:Silicone 
  • Access Method:Spectrum Steam

The Site

It was no wonder that many other contractors had deemed this an ‘impossible site’, a challenge that Spectrum was prepared to take on.

The Logistics

There were a lot of technical access challenges; However, there were also some political challenges too. The Bus station had rigorous protocols on health and safety, and if anyone were to gain access to the back of this bus station, they would need to undertake the same health and safety training their staff would have. The pub were not allowing any disruption to their garden especially during some of the busiest months of their year, gaining access to this would remain a challenge for Spectrum too.

With Spectrum considering all of the above. The method of cleaning would consist of combining two access strategies. 15% of the building would be cleaned via rope access in which an A-Frame portable anchor device would be brought to the site as there was no fixed anchor on the roof for the abseilers to use. The remaining 85% would be cleaned via the Spectrum Patented Render Cleaning System. This system would enable much of the work to be done from the safety of the ground without the use of any expensive and disruptive scaffolding, M.E.P.U. or specialist equipment. This access strategy alone was set to save the client over 30%! With an access method proposed, the political issues would need to be addressed for these planned works to be approved by all parties.

+plus point

The Housing Association saved £120K on access costs over 3 decorating cycles.

The Impossible Render Clean
Case Study

Spectrum Went Above And Beyond

To address the political challenges to this site, Spectrum conducted a tri-party meeting, to present a solution to the owners of the surrounding affected sites. Spectrum organised for their team to carry out the required health and safety training for them to gain access to the base of the bus and coach depot. The bus garage had also informed Spectrum that they had some roof and gutter issues. Spectrum carried out a full inspection for the bus garage as a thank-you for their cooperation to the planned works.

The pub were impressed by the fact that Spectrum would not need to use scaffolding around their pub to gain access to the block and as a gesture of goodwill for their collaboration on this project Spectrum had a credit note raised to them for future use which included a full external clean to their façade and windows.

+plus point
No Need For Scaffolding

Impossible, NEVER

Once all parties had confirmed they were happy to approve the cleaning works, Spectrum began restoring this building to its former glory. In just over 28 days, Spectrum had applied a biocidal wash, steam cleaned, and future-proofed each elevation with minimal disruption to all parties and the public. In addition to the render restoration, Spectrum had cleaned the stained decking, taken care of the gutters and cleaned all windows and surrounds. A building that had been deemed “impossible” to access and “impossible” to clean had been transformed with no risk to the public or environment.

Back to Case Studies

Read Our Render Cleaning Projects

How We Cleaned 15 Rendered Blocks In Kent In Under 5 Weeks

18th June 2020

+plus pointOur self contained vans carried 1000 litres of purified water to site each day.

In-Depth Stone and Brick Inspection

27th July 2021

+plus pointWe're proud to provide our clients with the best stone inspection and conservation service possible

Major Building Contract

18th January 2021

+plus pointOur team of operatives are trained and experienced in meeting the specific standards of work outlined in any major works contract.

Rope Access Stone Repairs

4th February 2021

+plus pointOur team of highly credible stone restorers were able to find the exact colour match for the stone by sending it to the lab.

When 3 Companies Couldn't Find An Access Solution We Knew We Had To Solve It!

18th June 2020

+plus pointOur patented cleaning equipment made this possible.

Eye Bolt Testing

20th October 2020

+plus pointUsing our expertise in working at height, we are able to assess all eye bolt and anchor safety points quickly and efficiently.

Torc Cleaning      

4th March 2021

+plus pointThe powerful yet gentle effects of the DOFF and TORC machines allowed us to remove signs of wear without leaving cracks.

Restoring Wooden Cladding with High-Temperature Steam

21st September 2020

+plus point70% saving in access costs - No scaffolding required.

Abseiling Sash Window Repairs

22nd January 2021

+plus pointAt Spectrum, we train our skilled decorator to abseil, ensuring they provide the highest quality refurbishments while also working at height!

Render Facade Restoration

1st July 2021

+plus pointAbseiling is a cost-effective method when it comes to façade cleaning

Can We Help With Your Specialist Building Cleaning and Restoration Needs?

Call Us On:

020 3551 6206

Email Us On:

info@spectrumss.co.uk

We Cover The WHOLE Of The UK!